A fast, accurate quote for a hybrid energy storage system depends less on how good the manufacturer’s sales engineer is and more on what you send them. Give a complete load profile, site grid data, an autonomy target, voltage and phase requirements, details of any existing solar or generator, and your logistics preferences, and a factory can return a specified, priced system on the first pass. Leave any of these out and you get a generic budgetary number that changes twice before the order is placed.
This checklist is written for the data you send before you ask for a number, not for the sizing math itself. For the step-by-step method, see our commercial battery storage sizing guide. This article covers what to hand over so someone else can size it correctly the first time.
Start with the load profile, not just a kW number
A single peak kW figure tells a manufacturer almost nothing about how the battery and inverter should be sized. What matters is the shape of the load over a full cycle: base load, peak load, how long the peak lasts, and whether anything on site has a large starting surge.
For a construction or mining site, list:
- Continuous (base) load in kW
- Peak load in kW and how many minutes or seconds it lasts
- Motor starting currents for pumps, compressors, crushers or conveyors (locked-rotor or starting kVA if you have it)
- Daily run pattern: 24/7, day shift only, or intermittent
- Power factor, if known, especially on sites with motor-heavy loads
For a residential or light commercial load, a 24-hour load curve in kWh (even an estimate from an existing bill) is more useful than a single peak figure. If several buildings or circuits are involved, list them separately rather than as one combined total: a manufacturer sizing a container-based system needs to know if 300 kW is one continuous process or ten intermittent circuits that rarely peak together.
Site country, grid frequency and connection type
State the country and, if relevant, the specific region or utility. This single line answers several questions the manufacturer would otherwise have to ask one by one: 50 Hz or 60 Hz, nominal voltage (230/400 V three-phase is standard in Australia; the US typically runs 120/208 V or 277/480 V depending on the service), and whether the unit will be grid-connected, off-grid, or switching between the two.
This matters for the hybrid units in this guide: the VMHV160K3 and VMHV500K3 datasheets list a 50 Hz, 3-phase 400/230 V output as standard, so a 60 Hz site has to be stated up front for the output to be configured accordingly.
Also say whether the site has an existing grid connection at all. A hybrid system that only ever needs to support a generator off-grid is a different quote to one that must synchronize with a weak or intermittent grid feed.
Set an autonomy target, even a rough one
Autonomy is how long the battery should carry the load without solar input or generator support. This is the number that drives battery kWh sizing more than almost anything else, and it is the figure most often missing from first-round quote requests.
A few examples of how autonomy targets change the answer:
- A peak-shaving application on a site with grid power might only need 1–2 hours of battery autonomy to trim demand charges.
- An off-grid mining camp wants several hours of night-time coverage from battery and solar before the generator needs to start.
- A disaster-relief or telecom backup application might specify 24–72 hours of full backup with no solar assumed.
If you genuinely do not have a target yet, say so and describe the risk tolerance instead (“we can accept the generator starting most nights” vs. “the generator must only run a few hours a week”). That qualitative answer is still more useful than silence.
Voltage, phases and output configuration
Confirm whether the load is single-phase or three-phase, and at what voltage. Most industrial and mining loads above about 30 kW are three-phase 400 V (Australia) or three-phase 480 V/208 V (US), but confirm it rather than assume it, especially on mixed sites with both three-phase machinery and single-phase site offices.
If the site has unusual requirements, such as a step-up or step-down transformer already in place, specific earthing arrangements, or a requirement to match an existing switchboard, mention them. These details change how the PCS is configured at the output (the power conversion system) and are far cheaper to flag before manufacturing than after.
Existing solar and existing generator: keep or replace?
Tell the manufacturer whether the project already has solar panels, a diesel generator, or both, and whether the hybrid system needs to integrate with that equipment or replace it outright.
If you want the hybrid system’s MPPT inputs to accept an existing solar array, give the array’s DC voltage range and total kW. If a generator already on site is staying there to run in parallel with the new hybrid unit, send its brand, model, rated kW/kVA and output voltage, because the genset interface and synchronization settings on the hybrid controller need to match it.
The VMHV160K3 ships with its own 100 kVA Perkins genset and four MPPT solar inputs, so new or existing PV can be fed into the same unit.
If the project has no existing generator and no existing solar, say that too. A clean-sheet site is actually the easiest to quote, because there are no legacy constraints to work around.
Logistics: destination, access and Incoterm
A hybrid ESS trailer or container has to physically get to site, and the logistics details change both lead time and total landed cost. Send:
- Destination port or final delivery address
- Site access constraints: crane availability, forklift access, ground conditions for a trailer, or restrictions on vehicle size
- Preferred Incoterm (for example FOB or CIF) so the manufacturer quotes on the basis you actually want to compare
- Whether the unit needs to fit a specific container size for onward shipping, or whether it will be trucked directly
A 160 kW trailer-mounted unit and a 250 kW containerized unit have different site footprints and craneage needs. The table below shows why this matters for logistics planning, not just capacity.
VMHV160K3 vs VMHV500K3: what changes for logistics and site planning
| VMHV160K3 | VMHV500K3 | |
|---|---|---|
| System power | 160 kW | 250 kW |
| Battery capacity | 225 kWh LiFePO4 | 482 kWh LiFePO4 |
| Diesel generator | 100 kVA Perkins | 250 kW Perkins 1706J |
| Solar input | 4 MPPT channels | 4 MPPT channels, up to 1,100 V |
| Format | Trailer, 6 t | 20 ft container, 15 t |
| Dimensions (L×W×H) | 3,320 × 2,170 × 2,230 mm | 6,058 × 2,438 × 2,591 mm |
| Container loading | 1 × 20 ft or 3 × 40 ft | 1 unit per 20 ft |
| Output | 3-phase 400/230 V, 50 Hz | 3-phase 400/230 V, 50 Hz |
A 6 t trailer can be towed to a laydown area by a suitable truck. A containerized unit needs crane or forklift access at both ends of the journey. If your site has limited lifting equipment, that single fact changes which format makes sense regardless of the kW rating. Between these two sizes sits the VMHV180K3 multimode hybrid ESS, rated 180 kW with a 241 kWh battery. If you are planning several units spread across one site rather than a single VMHV500K3 container, say so in the request: the answer then covers how the units share the site’s loads.
Factory-fitted breakers and cable runs inside a hybrid ESS cabinet, photographed prior to closing the enclosure.
Putting the checklist together
A complete request to a manufacturer should read something like this, filled in with your own numbers:
- Load profile: base load, peak load, motor starting currents, daily run pattern
- Site country, grid frequency, nominal voltage, grid-connected or off-grid
- Autonomy target, or a qualitative description of acceptable generator run time
- Voltage and phase configuration required at the output
- Existing solar array (kW, voltage range) or existing generator (brand, model, kW/kVA) to integrate with, or confirmation that none exists
- Destination, site access constraints, and preferred Incoterm
Sending all six points in one message, rather than answering them one at a time over several email threads, is what actually compresses the quoting timeline. It also means the number you get back reflects the project as it will really be built, not a placeholder based on assumptions. For background on how AB-iPower structures factory-direct hybrid ESS supply for EPCs, rental fleets and distributors, see the factory-direct hybrid ESS vendor overview.
Ready to send your project details
Gather the six points above (load profile, site country and grid data, autonomy target, voltage and phases, existing equipment, logistics preferences) and submit them through get a quote. A complete first message is the fastest way to get a specified, accurate number instead of a budgetary estimate that needs revising.
Frequently asked questions
What is the single most common reason a hybrid ESS quote comes back wrong?
Missing or vague load data. A procurement team sends a total connected load in kW with no breakdown of motor starting currents, duty cycle or peak events, and the manufacturer has to quote on assumptions. A load profile with surge values and run hours removes that guesswork.
Do I need to know the exact autonomy I want before asking for a quote?
You need a target, even a rough one such as 8 hours of battery-only operation or 3 days of backup. The manufacturer can refine the battery sizing once other data is in, but without any autonomy target they cannot separate a battery sized for peak shaving from one sized for extended outages.
Why does the manufacturer need to know my country and grid frequency?
Grid frequency (50 Hz or 60 Hz), nominal voltage and plug or connector standards affect the inverter, transformer and output configuration. Shipping to a US jobsite running 60 Hz three-phase requires a different configuration than a 50 Hz site in Australia, even if the kW rating is identical.
What if there is no generator on site yet?
Tell the manufacturer the hybrid system will run as a stand-alone installation. If a generator is already on site and needs to keep running in parallel, send its brand, model, kW/kVA rating and output voltage so the hybrid unit's genset interface and controls can be matched to it.
Does the Incoterm actually change the quoted price or just the shipping line item?
It changes what is included in the number you compare between suppliers. An EXW price stops at the factory gate, a FOB price includes delivery on board at the port of loading, and a CIF price adds sea freight and insurance to the destination port. Import duties and local delivery stay with the buyer under all three. Stating your preferred Incoterm up front lets the manufacturer quote on a like-for-like basis instead of guessing your logistics setup.