Rental fleets adding portable energy storage systems need units sized to the job, not one unit for every customer. The MP05K-12 (5 kW, 11.776 kWh), the MP12K-30 (12 to 15 kW, up to 30.72 kWh) and the VE30 K3-60 (30 kW, 61.44 kWh) cover three distinct rental uses: tools and site cabins, events and larger sites, and three-phase loads run alongside a diesel generator. This guide compares their output, battery capacity and solar input, and gives a sizing method based on connected load and hours between recharges.

Why battery size alone does not decide the right unit

Two mobile power stations with similar kWh can behave very differently on site if their inverter power and peak rating differ. A unit that cannot start a compressor or a pump motor is the wrong choice even with a large battery. The three models below are compared on rated output, peak power, battery capacity and solar input, the four figures rental customers ask about before they sign.

Model Rated output Peak power Battery capacity Solar input Best-fit rental use
MP05K-12 5 kW 10 kW 11.776 kWh LiFePO4 8.8 kW Hand tools, site cabins, small single-phase loads
MP12K-30 15 kVA (1-phase, 30V) or 12 kW (3-phase, 30C) 27 kW for 10 s (30V) or 24 kW for 5 s (30C) Up to 30.72 kWh LiFePO4 4 kW (30V) or 9 kW (30C) Events, larger job sites, telecom backup
VE30 K3-60 30 kW three-phase, 400 V 37.5 kW for 10 s 61.44 kWh LiFePO4 4 × 4 kW MPPT Three-phase site loads, runs alongside a diesel generator

For a spec-by-spec breakdown of the two smaller units, with a runtime formula, see our portable LiFePO4 power station comparison. Stocking a depot? Request a fleet quote with the number of units per model and your depot country.

Use case 1: tools and site cabins, MP05K-12

Site cabins, security lighting, laptops, chargers and hand tools often draw a few kilowatts on average, with short peaks when a drill or a saw starts. The MP05K-12 is sized for that profile: 5 kW rated, 10 kW peak for short start-up surges, and an 11.776 kWh battery that gives about 5.9 hours at a steady 2 kW load, before inverter losses.

MP05K-12 5 kW mobile LiFePO4 power station on a trolley The MP05K-12 on its trolley, sized for site cabins, small tools and single-operator jobs.

On a rental yard, the trolley format matters as much as the electrical figures: one person moves the unit by hand, without a forklift or crane. Its UPS switchover also makes it useful as backup for a site cabin’s existing supply, not only as a standalone source. Solar input up to 8.8 kW lets crews on multi-day jobs top up the battery from a solar array during the day rather than keep a small generator running, which matters on sites near homes.

Where this unit stops: three-phase loads, start-up surges above 10 kW, or a continuous load above 5 kW. That is where the next size up comes in.

Use case 2: events and larger sites, MP12K-30

Event rental is a mixed-load business: PA systems, food stall equipment, LED signage, coffee machines and charging stations on the same supply, often for long days over a weekend. The MP12K-30 comes in two versions: the MP12K-30V, with a Victron 15 kVA single-phase inverter at 230 V, and the MP12K-30C, a 12 kW three-phase unit at 400 V with both 400 V and 230 V sockets.

MP12K-30 mobile LiFePO4 power station enclosure with forklift pockets The MP12K-30 enclosure has forklift and crane points for moving between sites.

Both versions share the same IP54 enclosure, forklift and crane points, and a LiFePO4 battery built from 5,120 Wh modules up to 30.72 kWh, so a depot team handles both the same way. At 480 to 540 kg depending on version, a 20 ft container holds 8 units and a 40 ft container holds 18, a useful figure when stocking a new depot.

For events, the absence of engine noise and exhaust at the point of use is often a harder requirement than raw kilowatts. See our broader look at mobile power solutions for events for other formats beyond battery-only setups. The battery sets the limit, though: at an average 6 kW, 30.72 kWh lasts about 5.1 hours before inverter losses. For a full event day, plan solar input during the day, a recharge window, or a generator kept away from the crowd that recharges the unit.

Use case 3: three-phase loads with a diesel generator, VE30 K3-60

Construction and industrial jobs with welders, compressors or pumps need three-phase power and enough peak capacity to start a motor. The VE30 K3-60 delivers 30 kW of three-phase output at 400 V, with 37.5 kW of peak power for 10 seconds, backed by 61.44 kWh of LiFePO4 storage. It works off-grid or grid-tied, and the generator and storage can run in parallel for higher loads, including the customer’s own diesel generator.

At low load the system draws on battery alone, calling the generator into service only when demand rises, which keeps logged engine hours down. Our guide on the 30 kW mobile battery as a diesel generator alternative covers this logic in more detail. Four 4 kW MPPT solar inputs let a fleet add solar panels on longer jobs and lean less on the generator.

Rental and EPC companies quoting three-phase jobs can also read why EPCs and rental companies use 30 kW mobile battery storage.

Sizing logic: match battery energy to the hours between recharges

A simple check: divide the battery energy (kWh) by the average connected load (kW) over the hours the unit must run without recharging. The examples below are illustrative and exclude inverter losses. Always work from the customer’s actual load list.

  • Site cabin: MP05K-12, 11.776 kWh, average load 2 kW: about 5.9 hours before a recharge.
  • Event: MP12K-30, 30.72 kWh, average load 6 kW: about 5.1 hours, so most event jobs need a recharge plan between sessions or days.
  • Three-phase site: VE30 K3-60, 61.44 kWh, average load 15 kW with peaks up to 30 kW: about 4.1 hours on battery alone, which is why continuous multi-day three-phase work is better served by running it in parallel with a generator.

Across all three, battery capacity sets how long the unit runs between charges, while rated and peak power set what it can drive. Matching both figures to the customer’s load list avoids underpowered units on site and oversized units sitting on a job that does not need them. For sites beyond this three-unit range, our guide to sizing a commercial battery storage system walks through the same load-matching logic at a larger scale.

Voltage and frequency for North American and New Zealand fleets

The standard datasheets list 230 V single-phase (MP12K-30V) and 400 V three-phase (MP12K-30C and VE30 K3-60) outputs at 50/60 Hz. New Zealand sites use 230/400 V. Common site supplies in the US and Canada are 120/240 V split-phase, or 208 V and 480 V three-phase. As the manufacturer, we build each unit to the voltage and frequency of the destination country, including 120/240 V, 208 V and 480 V at 60 Hz. Tell us the voltage, frequency and socket types your customers need, and the exact configuration is confirmed in your quotation.

What a rental fleet manager checks beyond kW and kWh

A rental unit earns money only while it is out on hire, so the figures that decide its life in a fleet are not all electrical:

  • Cycle life. The MP12K-30 and VE30 K3-60 batteries are rated for more than 6,000 cycles (VE30 K3-60 at 25 °C), which sets how many hire periods a unit can serve before its capacity drops.
  • Handling between depot and site. The MP05K-12 moves by hand on its trolley; the MP12K-30 (480 to 540 kg) has forklift and crane points; the VE30 K3-60 weighs 1.3 t and is handled as plant equipment.
  • Outdoor exposure. The MP12K-30 enclosure is rated IP54 for units left outdoors on unattended sites.
  • Checking a unit without a site visit. The MP12K-30 includes WiFi monitoring, so depot staff can check state of charge before a technician drives out.
  • Noise rules. In battery mode none of the three runs an engine, which opens night work, events and sites near homes where a diesel generator is restricted.

Building the mix into a fleet

A fleet serving construction, events and three-phase industrial customers usually needs more than one tier, in a ratio that follows its own demand. Utilization records by job type over a season are a more reliable guide than catalogue figures alone. Fleets serving construction, events and rental customers can ask us for a proposed unit mix and container loading plan with their quotation.

To size your fleet mix, request a quote and send your typical load profiles by job type (kW, phases and voltage), the country of your depots, and the autonomy you want on battery between recharges.

Frequently asked questions

Which size of mobile battery should a rental fleet add first?

Start from the jobs you already rent generators for. If most of them are site cabins, lighting and hand tools under about 3 kW, a 5 kW unit like the MP05K-12 fits. If they are events and larger single-phase or mixed sites, the MP12K-30 (15 kVA single-phase or 12 kW three-phase, up to 30.72 kWh) covers more of them. Three-phase motor loads and jobs that keep a diesel generator on site point to the VE30 K3-60 (30 kW, 61.44 kWh).

Can these units replace a diesel generator completely?

For loads within their rated and peak power, with a chance to recharge between working periods, yes. For continuous three-phase loads over several days with little chance to recharge, the VE30 K3-60 pairs with a diesel generator and runs alongside it, cutting engine hours rather than replacing the generator outright.

How do we choose between the MP12K-30 and the VE30 K3-60?

Compare the connected load, not the rental duration. Single-phase sockets up to 15 kW fit the MP12K-30V, and three-phase loads up to 12 kW fit the MP12K-30C. Larger three-phase equipment, motor starting loads or jobs that run alongside a diesel generator call for the VE30 K3-60 at 30 kW and 61.44 kWh.

Do these power stations need solar panels to work?

No. Solar input is an extra charging source. The MP12K-30 charges from solar, the grid or a generator, and the VE30 K3-60 works off-grid or grid-tied and in parallel with a generator. Solar simply reduces how often a recharge from another source is needed.